Float or slack is one of the most misunderstood concepts in scheduling yet arguably one of the most powerful tools for managing time risk in projects. Float is the amount of time an activity can be delayed without affecting the overall project completion date or subsequent activities. Understanding and managing float allows project managers to identify flexibility, prioritize resources, and negotiate deadlines intelligently.

Types of Float:

Why Float Matters:

Practical Example:
An electrical wiring activity has 10 days of total float. If the task is delayed by 5 days due to material shortage, the project completion is unaffected, as 5 days of float remain. However, if delays accumulate beyond 10 days, the critical path shifts, potentially delaying the entire project.

Tips:

Summary: Float is your project’s built-in insurance policy against time risks. Managing and protecting float helps keep deadlines intact even in the face of uncertainty.