Duration estimation is the process of predicting how long each activity in a project will take. The accuracy of duration estimates directly impacts project success.

1. Estimating Techniques:

Several techniques are used to estimate durations, including:

Formula for Three-Point Estimating:

2. Example: Three-Point Estimating

Consider an activity with the following estimates:

Using the formula:

Thus, the expected duration for the task is 6 days.

3. Risk Buffers

Once durations are estimated, it’s important to add contingency buffers to account for risks. One method is to use a Risk Factor and multiply it by the estimated duration:

Example:

Thus, the final duration estimate is:

4. Benefits of Accurate Duration Estimating

By using these methods, project managers can develop more accurate schedules, reduce risk of delays, and ensure that resources are allocated efficiently.

Leave a Reply

Your email address will not be published. Required fields are marked *