Duration estimating is one of the most critical but challenging aspects of project scheduling. Without accurate duration estimates, even the best schedule is unrealistic, setting the project up for failure. Many planners fall into the trap of guessing durations or relying solely on optimistic assumptions. Instead, estimating should be a rigorous scientific process using historical data, productivity rates, and statistical methods.

Four Primary Methods of Duration Estimating:

Additional Tips:

Example:
A drywall installation crew installs 50 m² per day under ideal conditions, but factoring in weather, complexity, and crew fatigue reduces productivity to 40 m²/day. For 1000 m², duration = 1000 ÷ 40 = 25 days, not 20 days.In Summary: Duration estimating is a blend of art and science. Applying data-driven methods, incorporating risk, and leveraging expert insights turns guesswork into reliable forecasts that improve schedule credibility and stakeholder confidence